More Pictures and Updates

We have a well! As of May 1st we have confirmation that the land is inhabitable with the discovery of water at a depth of 340 feet. Here, that’s considered a shallow well. We have 2 gallons a minute which again, here that’s good. The well will fill a 2000 gallon cistern. Don’t ask me what we would have done without the well. Some folks still drive into town and buy water in tanks on the back of their pickups.
I’ve added more pictures today to the Factory and Blasting photo albums. You’ll even seen our kitchen cabinets which were installed in the last 48 hours.
Status as of May 2nd.

  1. Well is ready
  2. House should be finished at factory by May 9th.
  3. More blasting is needed for the cistern (2000 Gallons), septic tank, drain field, and foundation.
  4. Foundation needs to be done. My guess is within the next two weeks we’ll have that under way if not finished.

Jenny and I are unbelievably excited. Just a quick not of thanks to anyone who has bothered to read any of this stuff. We’ve drawn on the kind words of friend and relatives constantly during this very challenging time. Thank you!